What Professor Dahud Sangodoyin Said About Circular Road, Other Projects Awarded by Oyo Govt

The Executive Council of Oyo State considered the briefs presented by Ministry of Works and approved the award of the following projects:

1.Clearing of the North-EAST Segment of Circular road which commences from Badeku area along Ibadan/Ife expressway to Molarere on Moniya-Iseyin road(36.7Km).

The project was awarded to M/S PICORAOD COMPANY LTD at a sum of N3.5b for a duration of six months.The works include:Bush clearing (150m width), removal of top soil, construction of Culverts and some earth works.

2. The award of remodeling and renovation of Governor’s Lodge, Guest Chalets, Boys Quarters and Liaison Office at Ikeja Lagos.

The project is awarded to Messrs Feyton Lanreolu Associates limited at a sum of N332134999.05 for a duration of three months.

3. ⁠The award of asphaltic improvement of dualised Mapo-Oritamerin (0.5km) as Additional works on the Asphaltic improvementof dualised Bus stop Gate-Molete Bridge .

This project is awarded to M/S Ratcon Construction Company Limited at sum of N373809539.41.

Please note that Lot 2 roads under the Asphaltic Improvement of some selected roads in Ibadan Metropolis had been awarded to Ratcon Construction company limited.

The additional works involve : scarification, laying of lateritic subbase materials, StoneBase, binder course, wearing course, Road furniture and lane markings